Parking Demand Studies in Mississauga: Survey and Submission Requirements
Separate expected submission evidence—site, zoning, parking supply, survey methods and interval results—from conditional methods such as comparable-site analysis, seasonal adjustments and transportation demand management (TDM). Mississauga’s September 2021 Terms of Reference: Parking Utilization Studies for Site Specific Applications makes these distinctions for local applications. [1]

Use those terms as a jurisdiction-specific reference, not an Ontario-wide standard or confirmation of today’s requirements. Before commissioning work, confirm the reviewing municipality’s applicable brief and parking provisions.
Confirm the study route and submission requirements
Under Mississauga’s terms, reductions generally greater than 10% require a Parking Utilization Study; a relatively minor reduction, generally less than 10%, may be supported by a Letter of Justification based on operating and land-use circumstances. [1] Confirm the route for an exactly-10% reduction rather than assuming either category applies.
The study or letter is usually submitted with a rezoning or Committee of Adjustment application and should be prepared by a qualified consultant experienced in this work. [1] Divide the scope into:
- Expected evidence: application background; site location, access and zoning; applicable parking requirements; legal on-site supply and an approved site plan; tenant or residential information, including vacancies; survey methodology and conditions; and interval results separating legal, illegal and off-site parking. [1]
- Conditional methods: proxy-site evidence where an appropriate comparable exists; 95th-percentile analysis rather than peak demand; seasonal factoring when surveys miss peak season; and TDM support where relevant. These are not analyses required for every proposal. [1]
Reconcile supply, floor area and vacancies
Ask for a baseline schedule linking the approved site plan, legal parking count, zoning calculation, proposed supply and requested reduction. Use it to check these required details:
- Application and site: application type, proposed use, site history, reason for the study, address, surrounding uses, access, zoning, applicable general or special parking provisions, transit availability and previous parking-related Committee of Adjustment applications. Confirm zoning information with the Zoning Section. [1]
- Tenant schedule: unit number, business name, vacancy status, gross floor area (GFA) in square metres and operating hours. Identify future tenants or proposed uses for vacant units. [1]
- Residential schedule: vacant units, unit types and tenure, such as rental or condominium, with resident and visitor parking supplies shown separately. [1]
Check the floor-area denominator. Observed demand ratios use occupied GFA. In mixed-use developments, apply By-law standards to vacant GFA and proposed infill uses unless a reduced standard is sought for that infill use. Keep these components visible rather than applying an occupied-area survey rate across the property. [1]
Separate supply from demand. Illegal and off-site parking must be documented separately and included in observed demand, not added to legal on-site supply. For an unbuilt proposal with unknown tenant types and characteristics, the terms generally call for parking at By-law standards. [1]
Select defensible comparable sites
For a new infill use, the terms allow proxy-site evidence where the same use exists elsewhere, preferably in Mississauga, in a similar context. The consultant is responsible for selection and must explain why the sites should generate similar demand. [1]
Ask for a side-by-side comparison covering the following dimensions. This is a suggested review format, not a prescribed municipal template:
- Use and activity: land use and operating hours.
- Occupancy: occupied floor area, vacancies and anticipated uses of vacant space.
- Parking arrangements: legal supply, shared parking and relevant off-site parking.
- Context: surrounding uses and transit availability.
- Timing: survey season relative to peak business activity.
These dimensions draw on the terms’ site and survey information. Ask the consultant to explain material differences and why similar demand remains a reasonable expectation. Published literature and other municipalities’ standards may provide supporting evidence, but proxy selection still needs justification. [1]
Confirm count periods before fieldwork
The terms direct consultants to confirm survey dates, times and survey type with Mississauga Planning and Building at [email protected] before counting. The September 2021 terms generally recommend two to three survey days per week for two consecutive weeks, with observations every half-hour during business hours and no surveying over holidays. [1]
Match the schedule to the use and operating hours. The restaurant example is Thursday, Friday and Saturday during lunch and dinner periods—not a universal schedule for every use. [1] Include these requirements in the scope:
- Survey conditions: record days, times, observation intervals, weather, operating hours, assumptions and unusual circumstances affecting results. [1]
- Interval demand: for a freestanding use, mixed-use plaza, industrial complex or residential visitor-parking survey, capture vehicles in legal spaces, illegally parked vehicles—including those in aisles or fire routes—and off-site vehicles on streets or neighbouring properties. Keep illegal and off-site counts separate. [1]
- Seasonal coverage: explain whether dates capture peak business season. Counts outside that season may require a high-month or peak-demand factor. The terms point to Appendix A’s monthly-variation guidance, derived from Shared Parking, Second Edition. Document the basis for any adjustment. [1]
Test occupancy, duration and shared-use assumptions
Interval occupancy counts show demand at observation times; they do not establish arrivals, departures or length of stay. The terms distinguish interval counts from interview and duration methods. Do not accept an occupancy table as a turnover study. [1]
For one use within shared plaza, industrial or Business Improvement Area parking, the terms call for employee and patron interviews recording arrival and departure times, duration, travel mode and, for drivers, parking location. Tabulate results by interval. [1]
Duration monitoring is use-dependent and may involve tracking entries and exits. The terms identify a restaurant as needing a duration study, but not a place of religious assembly during a regular service. [1]
For a shared-use claim, request an exhibit that:
- Aligns each use’s demand across the same observation periods.
- Shows demand overlaps and where the claimed sharing benefit arises.
- Labels observations and assumptions, linking observations to count or interview records.
Check whether operating hours, seasonal peaks, vacancies or future uses could change the assumed overlap. The terms require operating-hour and vacancy information and address peak-season adjustments. [1] The cited terms do not state a universal comparable-site minimum, turnover threshold or fixed shared-use reduction percentage. [1]
Audit interval tables and calculations
Request the interval spreadsheet, not just the summary. The terms call for appendix data showing:
- Survey day and observation interval. [1]
- Total on-site parking supply and occupied GFA in square metres. [1]
- Legal, illegal and off-site parking separately, plus total observed demand. [1]
- Percentage of total capacity and observed demand per 100 m² of occupied GFA. [1]
- Separate residential visitor, resident and non-residential parking categories, where applicable. [1]
Add legal, illegal and off-site counts and compare the sum with total demand. Check that supply and occupied-area denominators remain consistent—or that changes are explained. These are arithmetic checks on the required fields, not additional submission rules.
The summary should identify peak observed demand, when it occurred and its duration. Peak demand is the conservative analytical option. For the 95th-percentile alternative, each survey day must contribute the same number of observations; if observations are removed, exclude the lowest ratios. [1]
If the report cites 85% peak-hour occupancy, retain its context: the terms describe a general industry benchmark for good parking-supply service, not an approval threshold or automatic reduction. [1]
Ask the consultant to show seasonal factors and each step translating surveyed demand into proposed-use demand. Keep observed counts distinguishable from adjusted projections.
Check TDM reductions for double counting
Existing-site surveys may already reflect transit access and surrounding land uses. The terms say further reductions need discussion in relation to future changes. [1] Ask for a reduction ledger separating measured demand, effects already embedded in counts, and proposed additional changes with evidence for each adjustment.
TDM reductions should use empirical analysis and research, with conservative impacts where market acceptance or direct comparables are uncertain. TDM does not replace a parking-demand survey. [1]
Supporting evidence may include proximity within 500 metres of a major transit station, secure bicycle parking or discounted transit passes. These are measures to assess, not automatic parking credits. [1]
For programme measures, identify implementation arrangements, the development stage and mechanism securing delivery, and the applicant’s acknowledgement that it will implement the measure. Potential mechanisms include conditions or warning clauses in purchase-and-sale, condominium or development agreements. The terms direct consultants preparing a TDM justification to the TDM Coordinator at [email protected]. [1]
Reconcile the final submission
Under the cited terms, the conclusion should summarise the applicable Zoning By-law requirement, study findings, recommended site standard, requested standard or variance, and any Payment-in-lieu spaces, where applicable. [1] Ask for a closing reconciliation with references to the supporting calculations.
Return unexplained supply differences, omitted illegal or off-site demand, inconsistent floor-area denominators, unsupported proxy transfers or repeated TDM credits for clarification. Request a limitations statement distinguishing observations from assumptions and identifying evidence gaps affecting the claimed reduction.
Before accepting the report, check that:
- The applicable municipal brief and survey arrangements are identified.
- Legal supply reconciles with the approved site plan.
- Occupied floor area and vacancies are accounted for.
- Count periods and seasonal treatment are explained.
- Interval tables distinguish legal, illegal and off-site demand.
- Shared-use and TDM adjustments are traceable to evidence.
Under the terms, the submission sequence is to confirm survey arrangements, conduct and document counts, append interval evidence, analyse applicable adjustments, and submit reconciled conclusions with the rezoning or Committee of Adjustment application. [1]