How to Choose ASTM E1105 Testing: A Guide for US Owners
Choose ASTM E1105 testing by requiring a proposal that connects each installed assembly to defined boundaries, agreed test conditions, acceptance criteria, and repair/retest records. Specify location-keyed photographs and witness responsibilities expressly rather than assuming they are included. [3][4][5]

- Define in the testing scope: purpose, locations, assembly boundaries, governing procedure, conditions and acceptance criteria. [3][4]
- Request as explicit deliverables: designated witnesses, location-keyed photographs, repair records and linked retest results. These are procurement requirements to negotiate, not an assumed reporting package. [3][5]
Define acceptance testing or leak investigation
Start by identifying the assignment: new-work acceptance against specified criteria, investigation of reported leakage, or separately scoped work addressing both. ASTM’s historical E1105-15 material, updated in February 2023, describes the method principally as assessing compliance with specified performance criteria and cautions that other procedures may be more appropriate for locating leak sources. [2]
ASTM E1105 covers field water-penetration testing of installed exterior windows, skylights, doors and curtain walls. [1] In the method described by E1105-15, water is applied outside while a static air-pressure difference is maintained across the assembly. [2]
A laboratory rating is not proof of installed performance. ASTM explains that supporting construction, mounting, sealing, shipping, handling, subsequent trades and environmental exposure can affect installed performance. [2] For acceptance work, ask whether the tested installation meets the agreed criteria—not whether the product previously earned a laboratory rating.
Keep the conclusion narrow. Lansen’s vendor guide cautions that a pass applies to the tested configuration at that point in time, not every opening or future condition. [3] Observing water alone does not establish its root cause; ASTM distinguishes performance testing from procedures intended to locate leakage sources. [2]
Require the proposal to state the question the work will answer and the conclusions it will not support. If you need acceptance and diagnosis, identify those tasks separately.
Mark the openings and interfaces to be tested
Ask for a marked elevation or plan with a unique opening ID for every proposed test, plus the assembly type, floor, elevation and number or area of specimens. Make it part of the proposal. Construction Canada’s discussion of AAMA 503 emphasizes specifying exact test areas; Lansen recommends agreeing on locations and assembly limits beforehand. [3][4]
Define the assembly boundary at each location. Identify fixed and operable portions, mullions, perimeter seals, frame intersections, receptors, subframes and flashing, as applicable—not simply “window testing.” Construction Canada describes chamber boundaries encompassing perimeter frame intersections, seals, subframes, receptors and flashing; Hightower Labs’ project example also included fixed and operable units and mullions. [4][5]
List adjacent wall, roof, curb and other construction joints as explicit inclusions or exclusions. ASTM’s scope permits assessment of joints between the assembly and adjacent construction when specified; do not assume those interfaces are covered because the window is included. [2][4]
Ask why each location was selected. For new-work acceptance, Construction Canada’s AAMA 503 discussion calls for representative construction rather than specimens selected solely because they show obvious problems. [4] For an investigation, identify reported leak locations and suspected pathways as questions to investigate, not established diagnoses. [2]
Lansen recommends considering corners, sills, movement joints and roofline or balcony interfaces—vendor recommendations, not universal ASTM requirements. [3] Have the qualified project team justify the count and area and specify how additional locations would be authorized. [4]
Use one entry per location: opening ID → assembly limits → included interfaces → exclusions → reason selected.
Have the specifier approve conditions and passing criteria
Have the qualified specifier approve the conditions for each test area. Require the governing project specification, standard edition, uniform or cyclic procedure, test pressure, exposure duration and controlling acceptance definition. Your role is to check that these decisions are documented, not select technical values yourself. [2][3][4]
ASTM E1105 is not an air-infiltration test. If a proposal includes air and water testing, distinguish their procedures and results. [2]
Make “passing” explicit. Ask the specifier to state what constitutes failure under the controlling documents and how water observations outside that definition will be recorded. Project criteria can differ; the method does not identify hidden, unobservable water within the specimen or address every adverse effect of water entering an assembly. [2][4]
Require an interior-observation plan, including finish removal and restoration needed for visibility. ASTM cautions that inaccessible surfaces behind finishes can limit in-service curtain-wall testing. Testing before interior finishes makes penetration points easier to see and errors easier to correct. [2]
Request readiness checks for plumb, level, square, operation and surface condition, plus confirmation that installation and applicable sealant cure are complete. [4]
Include weather-interruption and rescheduling terms. E1105-15 says testing should not proceed when wind gusts cause pressure fluctuations exceeding ±10% of the specified pressure. Have the specifier confirm the restriction against the contract’s governing edition rather than automatically carrying that older provision forward. [2]
Request witnessed records tied to each location
Make the report traceable: location ID → specimen boundary → conditions and criteria → observations → result → photograph references → follow-up item. Specify this as an owner-requested deliverable, not an assumed reporting format. [3][5]
Name the witness, arrange attendance and state their authority to stop work. Lansen recommends an authorized witness—such as the specifier, consultant or client representative—and observations recorded as they occur. These recommendations are not automatically included services. [3]
- Field record: Request actual test conditions, observation times, visible water locations, interruptions and departures from scope. Keep observations separate from proposed explanations and conclusions. [2][3]
- Photographs: Request an overview showing the specimen boundary, relevant detail views and images keyed to opening IDs and observation entries. Specify this linkage contractually. [5]
- Result: Require the tested configuration, observation limitations and follow-up references for unresolved findings. A pass applies to the tested specimen and conditions, not every window or future condition. [2][3]
As a reporting example, Hightower Labs, which identifies an Elgin, Illinois office, describes a full ribbon-window assembly passing, followed by a report with marked results and photographic coverage delivered within 48 hours. These are provider-reported outcomes from one project, not a guaranteed turnaround. [5] The cited case study does not state its geographic service area or establish that photographs were keyed to opening locations. [5]
When reviewing findings, distinguish where water appeared from why it entered. ASTM cautions that concealed water may escape observation and other procedures may be more appropriate for locating sources. [2]
Assign repairs, cure time and retest closeout
Before testing, name who can authorize further investigation and approve corrections. Separate responsibility for initial testing, forensic work, repairs, restoration and retesting. Construction Canada recommends assigning payment for initial testing, retesting and necessary forensic testing in the contract documents. [4]
Put the repair-to-closeout process in writing:
- Assign the work. Identify who approves corrections, performs repairs, protects adjacent work, arranges access and documents completion. Give each cost item a responsible party.
- Link repair records to locations. Request the opening ID, original leakage observation, approved correction, materials, completion date and confirmation of readiness for retesting.
- Set readiness requirements. Have the responsible specialist establish cure requirements. Lansen recommends adequate cure time and retesting corrected areas rather than closing a failed item through a punch-list note alone. [3]
- Control the retest. Name who approves its scope and conditions, what triggers additional testing, and how changed procedures or boundaries will be recorded.
- Close the record. Require the original test, repair evidence and retest result to share the same opening ID, with unresolved items identified.
Repair workmanship, warranty, cure length and the number or extent of retests need project-specific terms; this guidance does not fix them. [3][4]
Check the agency and itemized quote
Give bidders the same location schedule, boundaries, conditions, reporting requirements and repair/retest assumptions. Ask for explicit exclusions. Construction Canada emphasizes exact test-area descriptions and contractual allocation of testing costs. [4]
Check the agency, not just the proposal. Request relevant installed-assembly experience, personnel qualifications, equipment calibration, insurance and availability. Construction Canada describes AAMA-accredited laboratories or field-testing agencies in its AAMA field-testing discussion; have the specifier verify the accreditation applicable to your assignment rather than treating it as a universal ASTM E1105 requirement. [4]
Request itemized charges or clearly defined inclusions for:
- Site work: mobilization, access, chamber setup and each location.
- Evidence: witness coordination, reporting, location-keyed photographs and revisions.
- Additional work: finish removal and restoration, diagnostics beyond the agreed test, and return visits.
Obtain written terms for weather delays, inaccessible interiors, cancellation, remobilization and payment milestones. State who authorizes additional work and whether it requires a separate written price.
Hightower’s cited case study does not state standard service prices or booking and cancellation terms. [5] Obtain a project-specific quote and written commercial commitments rather than treating a completed-project account as a service package.
Approve the scope-to-closeout chain before booking
Return an incomplete proposal for clarification rather than assuming omissions are included. This instruction can serve as the procurement gate:
Please revise the proposal so each test location connects its defined assembly and interfaces to agreed criteria, witnessed observations, photograph references, assigned repair responsibilities and any retest record. Identify exclusions and who pays for additional work.
You are procuring a documented result for identified assemblies under agreed conditions, with explicit next steps—not blanket assurance about every window. [2][3]
References
- ASTM E1105 Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference | Building America Solution Center (pnnl.gov)
- E1105 Standard Test Method for Field Determination of Water Penetration of Installed Exterior Windows, Skylights, Doors, and Curtain Walls, by Uniform or Cyclic Static Air Pressure Difference (astm.org, 2023)
- Curtain Wall Water Testing: Mock-Up and Field Tests – Lansen (lansenwindows.com)
- Key considerations when field testing fenestration systems – Construction Canada (constructioncanada.net, 2025)
- FIELD TESTING (hightower-labs.com, 2025)