Geomembrane Leak Detection: Scope Requirements for Australian Owners
To compare geomembrane leak detection proposals, give bidders the same liner description and installation stage, then require mapped coverage, site-demonstrated sensitivity and a repair-to-retest evidence trail. Separate method prerequisites from owner-selected acceptance terms:

- Technical prerequisites: suitable conductive paths above and below the liner, electrical isolation and method-specific surface, backing and water conditions. [2][3]
- Contractual requirements: specify coverage, exclusions, defect-location evidence, repair records and retest deliverables.
- Regulatory obligations: check the asset’s approval conditions separately; TRI’s service page and the covered-geomembrane paper do not establish Australian mandatory survey stages or acceptance thresholds. [1][4]
1. Give bidders the same liner and installation-stage brief
Issue a shared annotated drawing. Ask each bidder to identify feasibility assumptions, site preparation and anticipated exclusions against it.
- Layout and stage: show survey boundaries, floors, slopes and walls, and whether the liner will be exposed or covered by soil, water or wastewater. TRI Environmental Services distinguishes exposed and covered surveys. [1]
- Liner build-up: show single- or double-liner construction, conductive backing or underlying conductive media, and intervening geotextile, geonet, geogrid, geocomposite or geosynthetic clay liner. Wikipedia’s general-reference article Electrical liner integrity survey explains why conductivity beneath the test liner affects feasibility. [2]
- Exposed-surface conditions: give slope angles and texture, wall dimensions, substrate contact, cleanliness, dryness and available water supply. HGI’s method descriptions identify these as suitability constraints. [3] If a bidder proposes a water-based method, ask them to specify the supply, flow and pressure their equipment needs at your site and who will provide it.
- Covered-liner conditions: describe cover thickness, composition, moisture and placement sequence, plus perimeter isolation and conductive penetrations. The 2018 covered-geomembrane dipole paper explains how these variables affect performance. [4]
Use a common bidder response schedule to record the proposed method by area, required preparation and exclusions. This is an owner-selected procurement tool, not a prescribed form.
2. Separate seam records from survey evidence
An electrical liner integrity survey searches for through-liner defects in the installed geomembrane. It should not be treated as verification of every weld parameter or a replacement for installation and seam-testing records. [2][4]
The stage determines what damage a survey can assess. Exposed-liner surveying can identify installation defects, including faulty extrusions and knife cuts. A covered dipole survey can locate punctures and tears introduced during protective-cover placement—damage an earlier survey could not assess. [4]
The covered-geomembrane paper recommends the following sequence as technical guidance: [4]
- Survey the exposed geomembrane.
- Repair detected defects.
- Place the protective cover.
- Conduct a dipole survey immediately after cover placement. [4]
Define contractual hold points. State what evidence is needed before cover placement and before acceptance, who releases each hold point, and how unresolved defects or survey limitations will be handled. These are recommended owner-defined controls.
For an operational asset, assess feasibility before requesting equivalent evidence. The paper warns that thick or heterogeneous cover and poor electrical isolation can make surveying difficult, identifying pre-commissioning as the preferable opportunity. A later survey should not automatically be treated as equivalent to an earlier-stage assessment. [4]
3. Choose methods by stage and site conditions
TRI Environmental Services offers exposed and soil- or water-covered liner surveys and states that it is Australia’s only ISO17025-accredited laboratory for liner integrity surveys. [1] Its service page references ASTM D6747 for method selection and ASTM D7007 and D8265 for water- or earth-covered surveys. [1]
HGI – Leak Detection’s descriptions provide technical comparisons below, not a verified competing Australian service option: its cited page does not state its service area. Production rates are HGI-reported averages per operator. [3]
- Water puddle — exposed liner. Check slopes and liner-to-substrate contact; HGI identifies poor contact as a limitation. [3]
- Water lance — exposed liner. HGI describes the water lance method as suitable for uneven surfaces, extreme side slopes and vertical walls, but identifies high water demand and poor liner–substrate contact as limitations; reported average: 900 m²/hour per operator. [3]
- Spark — new-construction bare liner. HGI's spark testing method requires conductive-backed geomembrane and a clean, dry surface; reported average: 500 m²/hour per operator. [3]
- Arc — new-construction bare liner. HGI’s arc testing requires new construction bare geomembranes, a semiconductive layer beneath the geomembrane and a clean, dry surface; reported average: 900 m²/hour per operator. [3]
- Covered dipole — earth- or water-covered liner. This method measures voltage potential on a grid over the covered area. Cover depth, moisture and conductivity affect detection. [2]
Do not convert these production averages into programme promises: they are vendor-reported survey rates, not total project durations or Australian scheduling commitments. [3]
4. Resolve access and coverage limitations
Electrical suitability is a prerequisite, not a reporting extra. Electrical surveys need conductive paths above and below the geomembrane and electrical isolation from surrounding ground. Water-based methods need a suitable water supply; spark testing requires conductive-backed geomembrane. [2][3]
Require an annotated coverage plan distinguishing proposed test areas, conditional areas and exclusions. Ask for the reason and proposed treatment for each exclusion, rather than accepting a quoted asset area as evidence of coverage.
- Exposed liners: require bidders to address slopes, walls, substrate contact, cleanliness, dryness and water access. HGI describes different constraints for each method. [3]
- Covered liners: require stated cover thickness and uniformity, moisture-conditioning responsibilities, layer sequence, survey grid and electrical-isolation arrangements. These affect meaningful coverage and detection. [2][4]
The covered-geomembrane paper explains that access roads, concrete structures and conductive penetrations can let current escape to surrounding ground rather than through liner defects. Rock cover can also impede electrical signals from a moist lower layer. [4]
Allocate responsibility for preparing and maintaining test conditions. Specify whether unsuitable conditions will be rectified, the method revised or an area declared untestable. Poor contact, unsuitable cover or lost isolation can impair detection or prevent surveying. [3][4] Require changed conditions and resulting exclusions to be documented before proceeding.
5. Compare sensitivity and location accuracy separately
A proposal should distinguish the smallest defect it can detect from how precisely it can locate it. Cover conditions affect both; detection does not necessarily provide a precise excavation point. [4]
Wikipedia’s Electrical liner integrity survey gives expected dipole sensitivities of a 6.4 mm-diameter defect beneath up to 600 mm of earth and 1.4 mm under water. Treat these as conditional background benchmarks, not promised site acceptance results. [2]
The covered-geomembrane paper explains that cover depth, moisture, mineralogy, heterogeneity and isolation can materially alter detectability. Its location examples illustrate a separate limitation: roughly 150 mm location accuracy beneath 300 mm of cover, compared with a 1–2 m perimeter beneath 1 m of cover. These are reported illustrations, not universal tolerances. [4]
Ask each bidder to address:
- Demonstrated sensitivity: propose calibration using simulated holes and record the smallest detectable defect under actual survey conditions, rather than relying on headline method capability. [4]
- Location uncertainty: state the anticipated uncertainty around mapped indications and explain the effect of cover conditions. [4]
- Inadequate calibration: agree whether conditions will be improved, the scope revised or the intended sensitivity recorded as not demonstrated. An unsuccessful calibration is not evidence of liner integrity. [4]
Set project-specific contractual targets: neither the general reference nor the covered-geomembrane paper establishes a universal Australian acceptance sensitivity or location tolerance. [2][4]
6. Specify a defect map and repair-to-retest trail
Require a report that follows each defect indication through repair and retest, rather than ending with an unexplained pass. HGI describes marking exposed-liner defects for repair; Electrical liner integrity survey describes grid measurements, data collection and voltage mapping for covered dipole surveys. [3][2]
Build on those practices with the following contractual deliverables:
- Survey record: stage and date, method and referenced standard, mapped coverage and exclusions, actual cover and moisture conditions, electrical-isolation conditions and calibration results. Site conditions and calibration affect what the survey can demonstrate. [4]
- Defect map: give each indication a unique identifier and coordinate or grid reference linked to its field marking. Request photographs where useful and stated location uncertainty. These proposed reporting terms build on field marking and mapped survey data. [3][2][4]
- Repair register: specify defect ID, repair location, repair evidence, responsible party and completion status, linked to the original indication and retest outcome.
- Retest and closure record: agree before award on the post-repair retest method, extent and evidence, how unresolved indications and untested areas will be recorded, and who signs off closure.
These register and closure requirements are owner-selected terms: the technical references do not establish a complete Australian defect-map format or mandatory repair-to-retest procedure. [2][4]
Keep survey, repair and retest evidence connected, without implying the survey validates every installation or seam-testing record. [2][4] A satisfactory result is evidence within the tested coverage and demonstrated conditions, not a guarantee of a leak-free installation in all conditions. [4]
7. Compare proposals against one acceptance checklist
Mark each item confirmed, conditional or not addressed:
- Asset and stage: the same liner construction, area and exposed or covered condition.
- Feasibility: suitable method, prerequisites addressed and preparation responsibilities allocated.
- Coverage: mapped boundaries, conditional areas and exclusions.
- Performance: site-demonstrated sensitivity and stated location uncertainty.
- Evidence: mapped defects, linked repair records and agreed retest evidence for closure.
Use these as procurement labels, not a published technical standard. Resolve conditional items before award, then check delivered evidence against the agreed scope before acceptance.
References
- Tri-Env Services | Liner Integrity Surveys | Tri-Env Services (tri-env.com.au)
- Electrical liner integrity survey – Wikipedia (wikipedia.org)
- Bare Liner Integrity Surveys | HGI – Leak Detection (hgileakdetection.com)
- Why covered geomembrane leak location (dipole) is … (geosyntheticssociety.org)