Bat surveys in England: requirements for building owners
Commission a suitably qualified ecologist to assess the proposed works, record inspection limitations and identify what bat evidence is needed before a planning decision.[1][2][4] Separate the requirements from the commissioning choices:

- Legal requirement: comply with bat protection law; planning permission does not replace any necessary bat mitigation licence.[1][2]
- Planning evidence: provide sufficient information to assess the effects on bats. Natural England advises councils not to decide applications until all necessary surveys have been received.[1]
- Recommended appointment scope: agree the inspection methods, written findings, justified follow-up recommendations and responsibility for next steps.[4]
- Local acceptance requirements: check the relevant council’s expectations rather than treating another council’s survey standard as a national minimum.[3]
1. Brief the ecologist on the works, not just the building
Commission an assessment of the proposed works, not simply a service labelled “bat survey”. Bat Conservation Trust (BCT) guidance links survey design to the proposal’s stage, potential impacts, objectives and proportionate survey effort.[4]
Give the ecologist a brief covering:
- The work proposed: specify whether it involves construction, demolition, extension, conversion, renovation or maintenance, and identify the parts of the building affected.[2]
- Roof and access changes: explain roof alterations and anything that could affect or obstruct a potential roost entrance. Lichfield District Council identifies these, alongside changes that could make a roost unsuitable, as local survey triggers.[3]
- Lighting: describe existing lighting and proposed changes around the building and nearby habitat.[2]
- Building and surroundings: flag nearby woodland or water, uneven roof tiles, large roof timbers, cracks, small openings, hanging tiles and timber cladding, particularly on south-facing walls.[2]
These details inform the ecologist’s assessment; they are not a DIY test for ruling bats out. Natural England warns that no bat records does not mean bats are absent: information for that location may be unavailable.[2]
As practical commissioning advice, rather than a prescribed national document list, share available proposal drawings, photographs, known access constraints and your intended programme. Suggested appointment wording is:
“Please assess how the proposed works could affect bats and potential roosts. Record the areas inspected and any inaccessible areas, explain the resulting uncertainty, and identify outstanding evidence. Please justify any recommended further surveys against the proposal.”
This follows BCT’s emphasis on project-led survey design, preliminary roost assessment limitations and next steps.[4]
2. Specify what the first assessment should deliver
BCT’s fourth-edition guidelines distinguish a preliminary ecological appraisal, comprising desk study and fieldwork, from a preliminary roost assessment (PRA) focused on buildings, other built structures and underground sites. Agree the methods and outputs rather than relying on the appointment’s label.[4]
For a building PRA, expect an internal and external inspection assessing suitability for bats, possible access points, signs of use—such as droppings, staining or bats—and the building’s relationship to surrounding habitat.[3][4] This establishes potential and records evidence found; an initial inspection does not conclusively prove or disprove bat presence.[3]
Ask for a written explanation connecting the findings to the proposed works. For each inspection limitation, ask how it affects confidence in the conclusions and the recommended next steps.[4]
The report should explain whether the evidence is sufficient to assess the proposal’s effects on bats or which further investigations are recommended, and why.[1][4] Identifying the need for more detailed surveys is a recognised purpose of preliminary appraisal—not necessarily a failure of the first appointment.[1]
3. Programme seasonal follow-up before fixing the application date
A PRA can be undertaken at any time of year, but follow-up surveys may need a particular season.[1] Before fixing your application date, ask the ecologist which evidence can be collected now and which must wait.[1][4]
Natural England gives these indicative survey windows, depending on what is being investigated:[1]
- Hibernation roosts: November to mid-March.[1]
- Summer roosts: May to August.[1]
- Foraging or commuting behaviour: April to October.[1]
- Swarming: August to October.[1]
These are purpose-specific windows, not interchangeable booking dates or a requirement to commission every survey listed.[1] BCT’s guidance addresses timing, weather, survey effort and limitations, so the programme should reflect the investigation needed.[4]
Request a written follow-up programme showing:
- The outstanding evidence and why it matters to assessing the proposed works.[1][4]
- The proposed method, appropriate season and justification for the timing and effort.[1][4]
- Weather or inspection limitations that could affect the programme.[4]
- The implications for planning submission and determination if necessary evidence remains outstanding.[1][3]
Lichfield District Council specifies May to the end of August for follow-up building activity surveys; this is local advice, not a universal prescription for every project in England.[3] Build the application programme around the necessary evidence, rather than assuming seasonal work can follow permission.[1]
4. Check survey effort against the project and the council
Check the basis for the quoted survey effort, not just the number of visits. Keep three sources of expectations separate:
- England-wide planning advice: Natural England sets expectations for appropriate methods, timing and sufficient evidence to assess the proposal’s effects.[1][2]
- Professional good practice: BCT guidance calls for proportionate survey design and justified professional judgement, rather than an inflexible prescription.[4]
- Local acceptance requirements: councils may specify what they expect submitted survey evidence to contain, as Lichfield does.[3]
Lichfield is a local example: its general acceptance standard includes a daytime internal and external survey plus at least two activity surveys, with sufficient people and equipment.[3] This is not a national minimum; the recommended effort should be justified for the project and checked against the relevant council’s expectations.[3][4]
Ask how the building, proposed impacts, inspection limitations and survey objectives lead to the recommended methods, staffing and follow-up effort.[4] Request written justification for departures from professional guidance, and agree who will resolve council queries about survey effort before further work is commissioned.[3][4]
5. Verify competence and agree report responsibilities
Ask who will undertake the work, what relevant experience they have, and whether they hold the appropriate current bat-survey licence for the proposed methods. Natural England expects suitably qualified, licensed ecologists using appropriate methods.[1][2]
Lichfield recommends obtaining several quotations because prices can vary considerably.[3] Compare them against the same checklist of methods, deliverables and follow-up responsibilities, rather than assuming similarly named packages are equivalent.
Agree the report contents before commissioning. Adapted from Lichfield’s local expectations—not a mandatory national template—the checklist should cover:
- Survey dates, surveyors, relevant experience and licence number where appropriate.[3]
- Weather conditions, a sourced desk study, detailed methods and a site plan.[3]
- Detailed results, recommendations and reasoned conclusions.[3]
- An assessment of the proposed works’ effects, inspection limitations, outstanding evidence and justification for further surveys.[2][4]
BCT’s guidance addresses reporting and review, and expects professionals to justify their judgement.[4] Ask for conclusions explaining what the evidence means for the proposal, not merely a record of observations.
As suggested contractual arrangements, rather than statutory report inclusions, agree who will answer planning queries, coordinate further surveys, revise the report following design changes and handle separately commissioned licensing work. Ask the quotation to distinguish included work from additional appointments.
Also ask whether the evidence will remain suitable for the intended submission date and what could trigger an update. Natural England expects evidence from the most recent appropriate season, subject to its licensing policy exception, and warns that out-of-date surveys can lead to refusal.[1][2]
6. Confirm the evidence needed before a planning decision
Do not assume missing seasonal evidence can be supplied after permission. Natural England advises local planning authorities (LPAs) not to decide applications until all necessary surveys are received. Conditions should not normally defer evidence needed to assess protected-species impacts; insufficient evidence can lead to refusal.[1]
Submission and validation are separate from determination—the decision on the application. Lichfield states that submitting a survey which identifies further work as necessary invalidates the application at submission. This is its local position, not a national validation rule.[3]
Natural England expects survey evidence to identify species, population size, roost type and importance, access points, and important nearby flight routes and foraging areas.[2] The proposal must also explain how harm will be avoided or mitigated, with compensation as a last resort—not merely document survey visits.[2]
Exceptions need justification. Detailed surveys may be unnecessary where effects on protected species are demonstrably unlikely; exceptional conditions can sometimes secure additional or updated surveys; and licensing policy 4 can allow reduced survey work with worst-case compensation in certain circumstances.[1]
Before submission, ask the consultant to identify outstanding evidence, check the LPA’s validation and determination requirements, and explain whether any proposed exception is justified for the project.[1][3]
7. Keep planning permission separate from bat licensing
Planning permission does not authorise work that breaches bat protection law: breeding sites and resting places remain protected even when bats are absent.[1][2] A separate bat mitigation licence may be needed, with support from a suitably experienced and licensed ecological consultant.[2]
The three licensing tests require an eligible purpose, no satisfactory less-harmful solution, and no harm to the population’s long-term conservation or survival.[1] Before granting permission, the LPA must be confident any necessary licence is likely to be issued.[2] Relevant pre-commencement protected-species conditions generally need to be discharged before a licence is issued.[1]
Agree who will advise on licensing, develop mitigation and take responsibility for monitoring or management requirements. These can extend beyond construction, including maintaining accessible, suitable roosts and supporting habitat.[2]
References
- Protected species and development: advice for local planning authorities – GOV.UK (gov.uk, 2014)
- Bats: advice for making planning decisions – GOV.UK (gov.uk, 2022)
- Ecology advice – Bat surveys (lichfielddc.gov.uk)
- Bat Surveys for (bats.org.uk)