Flood Risk Assessment: Requirements for Developers in England
For an English planning application, usually commission a flood risk assessment (FRA) where the site or proposal triggers one; agree separately whether planning-test evidence and a drainage strategy are required.[2][3] Before commissioning, use this checklist:

- Where an FRA is required: scope the site assessment, suitable flood data, levels, mitigation and supporting drawings.[2][3]
- Where planning tests apply: allocate sequential- and exception-test evidence separately from the FRA.[3]
- Where drainage requirements apply: include a sustainable drainage strategy within the FRA or as a separate document.[2]
- For the commission: name who supplies information, investigates gaps, prepares drawings and handles consultation and revisions.
1. Check whether the proposal needs an FRA
An FRA should accompany development—including minor development and changes of use—where any of these triggers applies:[2]
- The site is in Flood Zone 2, 3 or 3b.[2]
- It is in Flood Zone 1 and covers at least one hectare.[2]
- It falls within “Flood Zones plus Climate Change”.[2]
- It is in Flood Zone 1 with current or future surface-water risk, or the local Strategic Flood Risk Assessment (SFRA) identifies increased risk over the development’s lifetime.[2]
- It is in an area with critical drainage problems; the Environment Agency says these areas are currently designated only in Devon and Cornwall, and applicants should obtain the local standing advice from the LPA.[2]
- The development increases vulnerability and may be affected by sources other than rivers or the sea.[2]
Start with Flood Map for Planning and the local SFRA; a map search is not a site-specific assessment.[2][6] Live flood alerts describe current conditions, not planning-site evidence.[5]
A missing or unsatisfactory required FRA may lead to refusal. Simple, low-risk proposals may be self-assessed, but applicants will usually need a flood-risk specialist.[2]
2. Separate the assessment, planning tests and drainage
Do not commission an undefined “FRA report”. Allocate these conditional workstreams and identify how each will be documented:
- Sequential test: screening considers buildings, access or escape routes, land raising and other vulnerable elements exposed to current or future flood risk—not merely the building footprint.[3] Nominate who prepares evidence about reasonably available alternative sites.
- Exception test: required for highly vulnerable development in Flood Zone 2, more vulnerable development in Zone 3a, and essential infrastructure in Zones 3a or 3b.[3] Ask the consultant to identify and explain the test’s two elements, then agree who prepares the evidence for each and how it cross-references the FRA.
- Sustainable drainage strategy: required where development could affect drainage on or around the site or lies in a flood-risk area. It can sit within the FRA or be a separate document.[2] Name the drainage designer.
Sequential-test exemptions include householder development, non-domestic extensions with a footprint below 250m², most changes of use, and certain previously tested allocated sites where use and known risk have not materially changed.[3] The general change-of-use exemption excludes caravan, camping, chalet, mobile-home and park-home uses.[3]
A surface-water-only site can also be exempt where its FRA demonstrates lifetime safety without increasing risk elsewhere. These exemptions do not automatically remove the FRA requirement.[2][3]
Discuss the sequential-test area of search with the local planning authority (LPA) early, including alternative sites and any required checks on their current status.[3] Where required sequential or exception tests are not met, development should not be allowed.[1]
3. Assemble the applicant’s site information
Before requesting a quotation, mark which information is available and who will fill each gap. Treat these allocations as a proposed working arrangement, not prescribed professional roles.
- Applicant supplies available records: site address, location and boundary plan, proposal description, area in hectares and development type; existing and proposed layouts, drainage records, landscaping information and survey files.[2][3][4]
- Consultant verifies classifications and compatibility: establish the development’s vulnerability classification and check Table 2 of the Planning Practice Guidance to determine whether it is incompatible with the flood zone.[2] Also verify major-development or minor-extension status, relevant SFRA findings, and whether the site lies within 20 metres of a main river, including a culverted main river, a flood defence or a flow control structure, as identified in the Environment Agency’s standing advice.[3]
- Surveyor supplies missing levels: assessment levels should be relative to Ordnance Datum. Where suitable Ordnance Survey level information is unavailable, a qualified surveyor’s land survey is needed.[3] Agree who commissions it and checks its suitability.
Local example—Westminster: the council’s checklist also asks for a grid reference, unit numbers, existing drainage, expected development lifetime and its basis, existing and proposed users, changes to hardstanding and surface-water flow routes, basement access and escape arrangements, and plans relating floor levels to predicted flood depths.[4] These are local requirements, not a universal English checklist.
4. Specify flood data and modelling checks
Ask for an evidence schedule recording each dataset’s source, production date, purpose, limitations and suitability, proportionate to the development and flood risk.[3] Include:
- Data requests: Environment Agency Products 1 and 4 for all developments; work using its hydraulic modelling is also likely to need Products 5–7. Product 3 is discontinued.[2]
- Model suitability: check existing models against current risk, the latest datasets, current standards, sufficient site-scale detail and current climate-change allowances.[2]
- Model reporting: evidence checks and updates using the standard review templates. Even recent Environment Agency models may need updating because they were not designed to assess third-party development.[2]
- Other evidence: relevant information from the LPA/SFRA, lead local flood authority (LLFA), water and sewerage company and internal drainage board, alongside available groundwater and reservoir information.[2]
Separate the initial model review from additional modelling in the commission. Product 4 can take up to 20 working days; this is a data-supply timescale, not a consultant turnaround commitment.[2] Flood Map for Planning accuracy is not guaranteed, so obtaining data does not replace checking its suitability.[2][6]
5. Agree future conditions and safety
The FRA must consider current and future flooding from rivers, the sea, surface water, groundwater, overwhelmed drains or sewers, reservoirs, canals and other artificial sources, including interactions between sources.[1][2]
Agree the assessment lifetime and climate-change basis. National guidance assumes at least 100 years for residential development unless a different period is justified; at least 75 years is a starting point for non-residential assessment.[1] Ask the consultant to explain the allowances selected.
The general design events are river or surface-water flooding with a 1% annual probability, or tidal flooding with a 0.5% annual probability, each with an appropriate climate-change allowance.[1] The safety assessment should address:
- Flood depth, velocity, speed of onset and duration—not only mapped extent.[1]
- Safe access and exit during the design flood, and evacuation before an extreme 0.1% annual-probability event plus climate change.[1]
- Structural safety, essential services and residual risk if defences fail or their capacity is exceeded.[1]
Name who will translate the findings into architectural, site-level and access revisions.
6. Define the report and supporting drawings
Agree deliverables proportionate to the proposal and its risk. The standing advice identifies these report contents:[3]
- Proposal: site address, development description and applicable standing-advice information.[3]
- Assessment: current and future flood sources, climate-change allowances, estimated lifetime flood level and defence-breach or overtopping risk.[3]
- Design response: include finished-floor levels, flood-resistance and resilience measures, and supporting plans showing their incorporation; where floor levels cannot be raised as required, the Environment Agency’s standing advice calls for extra measures protecting the property to at least 600mm above the estimated flood level.[3]
- Consistent levels: assessment levels relative to Ordnance Datum, with surface-water banded depths compared against site land levels to derive a maximum estimated flood level.[3]
Agree a drawing register covering flood levels, proposed floors, access and mitigation, with a named author for each plan. There is no single drawing list suitable for every English site.[2][3][4]
Westminster’s checklist additionally asks for warning and contingency arrangements and access, egress and evacuation plans.[4] Before submission, cross-check the FRA, planning-test evidence, drainage strategy and architectural drawings against the same proposal.
7. Check local drainage and submission requirements
Before fixing the scope, check the LPA’s current validation list, SFRA, LLFA requirements and application-stage expectations. The drainage strategy must reflect national SuDS standards and relevant local requirements.[2] Confirm any applicable policy-transition arrangements directly with the LPA.
Westminster-only example: its checklist calls for an outline surface-water drainage strategy and GLA/Westminster Sustainable Drainage Proforma for outline applications; full, reserved-matters and discharge-of-conditions applications require a detailed strategy and the proforma.[4] Supporting information includes:
- Outline: topographical survey, existing drainage, outline geology and hydrogeology, and a conceptual SuDS layout linked to the existing network.[4]
- Detailed: ground investigation, infiltration rates and groundwater levels; storage and pipe dimensions; long and cross sections; and maintenance, access and construction arrangements.[4]
Use these distinctions to allocate drainage calculations, infiltration investigations, detailed drainage design and maintenance documentation. Check the applicable local requirements rather than treating Westminster’s checklist as a national specification.
8. Assign consultation and design follow-up
Name who contacts the LPA and relevant risk-management authorities, answers technical comments, updates drawings and checks consistency before submission. Early consultation can identify necessary controls; consultees may include the Environment Agency, LLFA, internal drainage board, sewerage company and emergency planners.[1]
Agree whether the commission includes consultation responses, design iterations and revised calculations, and how additional work will be authorised.
Build in specialist escalation: Environment Agency standing advice recommends structural-engineer advice where a design would exclude more than 600mm of water.[3] Allocate checks for separate river, watercourse, floodplain or drainage-byelaw permissions and consents; planning permission does not guarantee those consents.[3]
Before accepting the scope, check it identifies the applicant’s inputs, missing investigations, conditional planning tests, drainage work, model checks, report and drawings—and the person responsible for consultation and revisions.
References
- Flood risk and coastal change – GOV.UK (gov.uk, 2014)
- Flood risk assessments: applying for planning permission – GOV.UK (gov.uk, 2014)
- Preparing a flood risk assessment: standing advice – GOV.UK (gov.uk, 2012)
- Flood Risk Assessment Checklist Site Details Development Site (westminster.gov.uk)
- Check for flooding in England – GOV.UK (service.gov.uk, 2026)
- Get flood risk information for planning in England – Flood map for planning – GOV.UK (service.gov.uk)